Reconstruction of the internal road in Brodnica at Wiejska Street

Reconstruction of the internal road in Brodnica at Wiejska Street

Reconstruction of the internal road in Brodnica at Wiejska Street

Road Reconstruction Agreement Signed. On January 27th, the Deputy Mayor Krzysztof Hekert signed an agreement with REJBUD at the Brodnica City Hall for the reconstruction of the internal road between Wiejska Street and the Circle K gas station in Brodnica.

Scope of Work: The investment includes the reconstruction of a 127.03 m long section of road, including the construction of a new pavement made of concrete paving stones (3.5 m wide) and openwork slabs (3.0 m wide). Shoulders will be constructed on both sides of the road, and a variable-width earthen shoulder will also be added on the left side.

Drainage: The project also includes the construction of a surface drainage system with rainwater discharge to the designed stormwater drainage system. As part of the works, a stormwater drainage network with inlets, connections, and manholes will be built.

Contractor and Costs: The contractor is REJBUD. The investment is worth PLN 239,850.00 gross, and the deadline for completion is 150 days from the date of signing the contract.